Yarrow (achillea millefolium).
Ecology: on dry to moist, well drained, open sites, meadows, rocky slopes, gravel bars, roadsides, open forest, low to high elevations, often weedy at lower elevations, common and widespread
Other notes: possibly too invasive for this application
Plant information sourced from: Mackinnon, Andy and Jim Pojar. Revised Plants of the Pacific Northwest Coasts. Lone Pine Publishing, c. 2004.
Readers- Please let us know if you have additional information of interest regarding the plants above (invasive species, non-hearty plants, etc.).
Other plants of interest:
Musk-flower (mimulus moschatus).
Ecology: stream banks, moist meadows, rocky seepage area, thickets, road sides, other moist shaded areas, low to mid elevations
Other notes: perennial
Fern (cystopteris fragilis).
Ecology: cool, moist to dry, often calcium rich, rocky forest and openings, rock cliffs/crevasses/ledges, talus slopes

Maidenhair Fern (adiantum pedatum).
Ecology: shady, hummus-rich sites, and moist often rocky forests, on steam banks, cliffs, and in the spray zone of waterfalls
Above plant information sourced from: Mackinnon, Andy and Jim Pojar. Revised Plants of the Pacific Northwest Coasts. Lone Pine Publishing, c. 2004.
Comfrey (also comphrey) is an important herb in organic gardening, having many fertilizer and purported medicinal uses. Comfrey is a particularly valuable source of fertility to the organic gardener. It is very deep rooted and acts as a dynamic accumulator, mining a host of nutrients from the soil. This plant is present on the proposed installation site, and may be incorporated into the design.
Source: Wikipedia
FLOW VOLUME CALCULATIONS
Average Stormwater Volume Conditions for Eugene, OR
Monthly inches and hours given are averages over a 50 year period.
January: 7.9in / 143hrs = .055in/hr
February: 5.5in /112hrs = .049in/hr
March: 5.3in /118hrs = .045in/hr
April: 3.1in /73hrs = .042in/hr
May : 2.3in / 54hrs = .043in/hr
June: 1.4in /32hrs = .044in/hr
July: .5in / 9hrs = .055in/hr
August: .9in /16hrs = .056in/hr
September: 1.4in / 25hrs = .056in/hr
October: 3.6in /65hrs = .055in/hr
November: 7.5in /126hrs = .057in/hr
December: 8.3in /140hrs = .059in/hr
Site A: Peak stormwater volumes accumulated in 1hr from the Urban Garden ceramics shed roof.
Roof area = 150 sq ft
Average Peak Volume (December) = .059in/hr = .036gal/hr
Max Recorded Volume = 1.14 in/hr = .71gal/hr
Surface Area of Roof X volume of stormwater gives:
AVERAGE 5.52gal/hr = .09gal/min
MAX RECORDED 106.59gal/hr = 1.78gal/min
Site B: Peak stormwater volumes accumulated in 1hr from the Urban Garden potting shed roof.
Roof area = 288 sq ft
Average Peak Volume (December) = .059in/hr = .036gal/hr
Max Recorded Volume = 1.14 in/hr = .71gal/hr
Surface Area of Roof X volume of stormwater gives:
AVERAGE 10.59gal/hr = .18gal/min
MAX RECORDED 204.48gal/hr = 3.41gal/min
PROJECT SCHEDULE
7.13.10 Tuesday
Clean up fascia board
Pick up sample materials
Construction process photos
7.14.10 Wednesday
Create title
Take construction process photos
Complete design drawings
Complete construction drawings
Condense habitat template
Flow calculations
Test fasteners
Upload Midterm Blog Posts:
Presidents, DDs, CDs, renderings, habitat template, process photos
7.15.10 Thursday
Midterm Due
Site clean up
Grade site
Infiltration test (x2)
Remove existing fascia board
Replace fascia board
Weekend
Revise construction drawings
7.19.10 Monday
Purchase materials
BRING, Jerry's, Eugene Sand and Gravel, Lane Forest Products
Begin constructing Fence drainage systems
7.20.10 Tuesday - 7.22.10 Thursday
Fence drainage project
Construct Fence drainage system and infiltration pit
7.26.10 Monday - 7.29.10 Thursday
Potting Shed project
Construct Potting Shed drainage system and infiltration pit
8.1.10 Sunday
All construction complete
8.2.10 Monday
Purchase all plants needed
Plant infiltration garden and drainage systems
8.3.10 Tuesday
Finishing touches
Document (photograph) projects on-site
8.4.10 Wednesday - 8.5.10 Thursday
Off
8.9.10 Monday - 8.10.10 Tuesday
Compile Final Drawings and Documents
Photographs, final drawings and renderings, final written statement
Upload Final Blog Posts
8.11.10 Wednesday
Final Project Due
CONSTRUCTION PROCESS PHOTOS